Schedule the following activities are part of a project to be scheduled using CPM. Activity Immediat 1 answer below »

Schedule the following activities are part of a project to be scheduled using CPM. Activity Immediate Time (Weeks) predecessor A A 4 C 3 2 С, D E 5 2 G F 2 Е, G Н a) Draw the network (4 Points) b) What is the critical path? (2 points) c) How many weeks will it take to complete the project? (2 points) d) Which activities have slack, and how much? (2 points)