Question 1. Question : A graph that plots the total resources needed per period vs. time is called a

Question 1. Question : A graph that plots the total resources needed per period vs. time is called a

Question 1. Question:A graph that plots the total resources needed per period vs.time is called a(n) __________.
:Gantt ChartResource Loading ChartWork Breakdown StructureProject Network ChartPERT/CPM Chart
Question 2. Question:Considering the following Activity-On-Node (AON) project(activity completion times are in days), what is the slack time associated withactivity E?
Activity-On-Node
Click here to view a Word version of the project.
0 days1 day2 days3 days3of 3
Question 3. Question:Considering the following Activity-On-Node (AON) project(activity completion times are in days), how long will it take to complete theproject?
Activity-On-Node
Click here to view a Word version of the project.
13 days14 days15 days16 days3of 3
Question 4. Question:Consider the following Activity-On-Node (AON) PERT project.The three values that represent each activity’s completion time (in days)correspond to an optimistic time, most likely time, and pessimistic time,respectively. What is the standard deviation associated with the completiontime of activity B?
Activity-On-Node-2
Click here to view a Word version of the project.
0.0245 days0.6667 days0.3145 days0.3333 days3of 3
Question 5. Question:Consider the following Activity-On-Node (AON) PERT project.The three values that represent each activity’s completion time (in days)correspond to an optimistic time, most likely time, and pessimistic time,respectively. What is the expected completion time of activity A?
Activity-On-Node-2
Click here to view a Word version of the project.
2 days3 days4 days5 days3of 3
Question 6. Question:Jamie is planning a trip overseas. A variety of activitiesmust be completed before her departure. The following table describes therelationships between these activities:
ImmediateActivityPredecessorsA –B AC AD B, CE B, CF D, EG F
Jamie was also able to estimate the activity times as shownin the table below:
Activity Time(Days)A 4B 4C 5D 3E 3F 2G 1
Considering the information above, what is the length of theproject?
11 days12 days14 days15 days3of 3
Question 7. Question:Consider the following set of activities that must becompleted in order to prep a new home for painting:
ImmediateActivityPredecessorsA –B –C A, BD CE CF D, EG EH F, G
Also assume that the painters were able to estimate theactivity times as shown in the table below:
Activity Time(Days)A 3B 2C 4D 5E 3F 2G 4H 2
Considering the information above, what is the earliestfinish time for activity F?
10 days12 days14 days16 days3of 3
Question 8. Question:Consider the following set of activities that must becompleted in order to prep a new home for painting:
ImmediateActivityPredecessorsA –B –C A, BD CE CF D, EG EH F, G
Also assume that the painters were able to estimate theactivity times as shown in the table below:
Activity Time(Days)A 3B 2C 4D 5E 3F 2G 4H 2
Considering the information above, what is the criticalpath?
ACDFHIN ACEFHBCDFHBCEGH0of 3
Question 9. Question:Francisco is planning a vacation to Germany. A variety ofactivities must be completed before his departure. The following tabledescribes the relationships between these activities:
ImmediateActivityPredecessorsA –B –C –D A, BE CF D, EG EH F, GI FJ I, H
Francisco was also able to estimate the activity times asshown in the table below:
Activity Time(Days)A 3B 4C 5D 3E 2F 1G 4H 3I 2J 5
Considering the information above, what is the slack foractivities F and G respectively?
0 days; 0 days3 days; 0 days4 days; 3 days4 days; 0 days3of 3
Question 10. Question:Francisco is planning a vacation to Germany. A variety ofactivities must be completed before his departure. The following tabledescribes the relationships between these activities:
ImmediateActivityPredecessorsA –B –C –D A, BE CF D, EG EH F, GI FJ I, H
Francisco was also able to estimate the activity times asshown in the table below:
Activity Time(Days)A 3B 4C 5D 3E 2F 1G 4H 3I 2J 5
Considering the information above, what is the earliestfinish time for activity E?
5 days6 days7 days8 days3of 3