Complete an Activity-on-Node (AON) network and upload to Moodle. You are allowed only one file… 1 answer below »

Complete an Activity-on-Node (AON) network and upload to Moodle. You are allowed only one file… 1 answer below »

Complete an Activity-on-Node (AON) network and upload to Moodle. You are allowed only one file upload.
~~~~~~~~~~~~~~~~~~~~~~~
You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 15 workings days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 15 working days.
Draw a project network given the information below. Complete the forward and backward pass, compute the activity slack, and identify the critical path. Do you expect to receive a bonus or a penalty on this project?
ID Description Predecessor Time (in days)
A Pour foundation None 3
B Erect frame A 4
C Roof B 4
D Windows B 1
E Doors B 1
F Electrical B 3
G Rough-in-frame C, D, E, F 2
H Door Opener E,F 1
I Paint G,H 2
J Cleanup I 1