Assume the network and data that follow. Compute the total direct cost for each project duration…. 1 answer below »

Assume the network and data that follow. Compute the total direct cost for each project duration. If the indirect costs for each project duration are $450 (21 time units), $400 (20), $350 (19), 300 (18), $250 (17), and $200 (16), compute the total project cost for each project duration. What duration represents the lowest total project cost? What is this cost?