(8) Given the following values for AC, PV, and EV along with the Critical Ratio Limit Chart, answer the following questions: AC = $7373 PV = $15, 975 EV = $9585 a. Determine the Critical Ratio for this project. b. Given the Critical Ratio Limit Chart, determine what actions, if any, are required.